Risk Register — Energy Per Intelligence Build Schedule
| ID |
Risk |
Impact |
Mitigation |
| R1 |
Metering IC breakout board out of stock or long lead time |
HIGH |
Order from 2 suppliers. Backup IC ready. |
| R2 |
CT clamp accuracy worse than datasheet spec |
MEDIUM |
Calibrate against reference meter. Budget for 2% error. |
| R3 |
distributed-llama incompatible with baseline models |
MEDIUM |
Test in Phase 1. llama.cpp server as fallback. |
| R4 |
JLCPCB fab lead time exceeds 2 weeks |
MEDIUM |
Order early. PCBWay as backup fab house. |
| R5 |
Benchmark scores inconsistent (high variance) |
MEDIUM |
3 repetitions with median. Lock governor and services. |
| R6 |
Pi 5 power draw too low for CT clamp resolution |
LOW |
SCT-013-005 (5A) for better low-current resolution. |
| R7 |
Orchestrator SQLite corruption during long recording |
LOW |
WAL mode. Hourly checkpoint. Backup CSV export. |
| R8 |
NemoClaw skill fails on production surgery run |
MEDIUM |
n8n retry logic with CEO alert. Manual fallback. |
| R9 |
Mixed-signal PCB layout creates analog noise |
MEDIUM |
Guard traces. Separate grounds. Breadboard-validated first. |
| R10 |
Baby arrives before autonomous operation |
HIGH |
All phases target May 2026. Breadboard data by Week 3. |