RISK REGISTER — EPI Build Schedule (SCHED-EPI-001) #347

@Franzabner

Description

@Franzabner

Risk Register — Energy Per Intelligence Build Schedule

ID Risk Impact Mitigation
R1 Metering IC breakout board out of stock or long lead time HIGH Order from 2 suppliers. Backup IC ready.
R2 CT clamp accuracy worse than datasheet spec MEDIUM Calibrate against reference meter. Budget for 2% error.
R3 distributed-llama incompatible with baseline models MEDIUM Test in Phase 1. llama.cpp server as fallback.
R4 JLCPCB fab lead time exceeds 2 weeks MEDIUM Order early. PCBWay as backup fab house.
R5 Benchmark scores inconsistent (high variance) MEDIUM 3 repetitions with median. Lock governor and services.
R6 Pi 5 power draw too low for CT clamp resolution LOW SCT-013-005 (5A) for better low-current resolution.
R7 Orchestrator SQLite corruption during long recording LOW WAL mode. Hourly checkpoint. Backup CSV export.
R8 NemoClaw skill fails on production surgery run MEDIUM n8n retry logic with CEO alert. Manual fallback.
R9 Mixed-signal PCB layout creates analog noise MEDIUM Guard traces. Separate grounds. Breadboard-validated first.
R10 Baby arrives before autonomous operation HIGH All phases target May 2026. Breadboard data by Week 3.

Risk Status

  • R1 mitigated - [ ] R2 mitigated - [ ] R3 mitigated - [ ] R4 mitigated - [ ] R5 mitigated
  • R6 mitigated - [ ] R7 mitigated - [ ] R8 mitigated - [ ] R9 mitigated - [ ] R10 monitored

SCHED-EPI-001 v1.0 | YOSO-YAi LLC

Metadata

Metadata

Assignees

No one assigned

    Labels

    critical-pathOn the critical path — delays cascade

    Projects

    Status

    Todo

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions