Modelling the Ideal Datacenter: One Checked Campus Stack
+One checked stack for a whole data-center campus: the building, the cooling plant, and the software gate that decides what may change — so a scheduler sees the load floor, the recooling limit, and the thermal budget before it places a single job.
+Manipulate the mechanism directly
++ How to read: Drag the slider from 0% to 100% of the 10 MW nameplate. Watch the load bar cross the 5.6% floor: below it the campus stops cooling itself and the air-side load must move to the aquifer loop; above it the sorption loop, the PCM budget, and the margin radius hold the contract. +
+Campus Contract Sizer: Load Floor, Recooling Limit & Thermal Budget
+Live solver from optifab/verify.py: test the 0.56 MW load floor, the 41.5 °C second-law recooling limit, the 2,500 kWh_th PCM budget, and the 2.85–2.96 MW of unlocked IT load.
+How a crew actually runs this
+Clone the 36 pinned repositories, run python3 verify.py; every figure must reproduce results/certificate.json.
plant_gate must pass all 15 Weft weight-update vectors and match Weft's own function on the 100,000-case differential test.
Run python3 verify.py --formal: the comparator accepts 8 theorems under 6 kernels and replays all 50 ledger decisions.
Pack the 12 margins, budget, load, recooling temperature, and time into the 64-byte frame; flag recooling_not_measured if the slot is empty.
Propose · Verify · Sign, measured runs, and untested limits
+One physical structure holding four organisations' work — aska-physical's building, thermal plant, and sensors; Foundation-0's mathematics; Moissanite-Labs' Weft gate; Proven-Commons' bar for verified software — mapped as 41 repositories and 43 links.
verify.py recomputes all 15 findings from pinned certificates and runs 24 must-fail controls; the exact gate passes Weft's 15 vectors and agrees with Weft's own function on 100,000 generated cases; the Lean comparator accepts 8 theorems under 6 kernels.
Claimed, not signed. An AI agent wrote v0.2.0 and no person has reviewed it; under the Foundation-0 rule a person signs, nothing here counts until a named person has reviewed it.
| Contract Term | Workload Must | Plant Offers | Gate | +
|---|---|---|---|
| IT load | Stay above the 0.56 MW floor, or move air load to the aquifer loop | PUE 1.074, no water, if recooling < ~41 °C | MODEL §3 |
| Cooling outage / burst | Charge every outage and burst above capacity to the thermal budget | 15 min ride-through at full load | MODEL §4 |
| Margin moves | Keep the margin vector within 0.1989 of the certified point | Rack vibration at 17.9% of its limit | MODEL §5 |
| Capacity planning | Plan capacity in IT power, not utility power | 2.85–2.96 MW more IT than a conventional plant | MODEL §1 |
+ Untested: No sensor feeds the chain and no valve, load, or machine obeys the gate; the plant model, the margins, the proposer, and the Python are unproved; the recooling temperature is absent from the funi-frame certificate; a real sorption machine needs a manufacturer's curve to confirm COP 0.62 at 58 °C drive. +
+Generated shop ticket (optifab-plant-gate.toml)
+Updates live with the sizer above. Copy it into the repo's check run.
+