[Epic] Phase 6: Production Deployment & Market Launch #19

Description

@Mullassery

Phase 6: Production & Support (Weeks 18-24)

Priority: HIGH
Duration: 5 weeks
Estimate: 45 hours

Focus: Release v2.0.0 to all channels, establish support

Key Deliverables

  • ✅ v2.0.0 released to PyPI, Homebrew, Docker
  • ✅ Cursor MCP server deployed (enable 360K Cursor users)
  • ✅ Production monitoring active
  • ✅ Support system in place
  • ✅ v2.1 roadmap finalized

Tasks

6.1 Release & Distribution

  • Build PyPI wheels (2h)
  • Publish to PyPI (1h)
  • Update Homebrew formula (2h)
  • Build Docker image (2h)

6.2 Production Monitoring

  • Setup logging pipeline (3h)
  • Setup Prometheus metrics (3h)
  • Setup distributed tracing (3h)
  • Create Grafana dashboards (2h)

6.3 Cursor Integration Deployment

  • Deploy Cursor MCP server (2h)
  • Enable Cursor users to access PrismNote (1h)

6.4 User Support

  • Support documentation (4h)
  • FAQ & troubleshooting (3h)
  • Monitor GitHub issues (5h)
  • Community engagement (5h)

6.5 Feedback & Planning

  • Collect user feedback (3h)
  • Analyze usage metrics (4h)
  • Prioritize feature requests (2h)
  • Plan v2.1+ roadmap (3h)

Related

Activity

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Assignees

No one assigned

    Labels

    No labels
    No labels

    Projects

    No projects

      Milestone

      No milestone

      Relationships

      None yet

      Development

      No branches or pull requests

      Issue actions