This milestone is a placeholder for issues that were identified as part of the system integration test but are not going to be addressed during the time frame of the project. (September 2014). Also search the issues for anything tagged 'wontfix'.
No due date•0/1 issues closedDevelopment of new features should end around 15 Sep to allow for a review and polish phase prior to the end of the project on 30 Sep.
Overdue by 11 year(s)•Due by September 15, 2014•1/2 issues closedFor project closure, all project documentation should be updated, any funding and payment issues should be resolved, and upper management and external stakeholders formally notified of the completion of project activities.
Overdue by 11 year(s)•Due by October 31, 2014