M2-00: Hackathon delivery tracker and GitHub setup #21
Type: Parent Tracker / Project Setup
Priority: P0
Initial status: Ready
Owner: Maintainer or Product/Ops
Depends on: none
Blocks: no code; controls all later work
Writable: GitHub milestones, labels, tracker bodies and relations
complete changed-path set: exactly the 18 authorized paths
unresolved review threads: 0
merge state: CLEAN
Both prior trust-boundary findings are closed. Independent Node 22.23.1 / pnpm 11.16.0 Maintainer verification passed adapter build/typecheck, 5 adapter files / 38 tests, public package import, full pnpm check with 21 files / 728 tests, browser bundle scan, production start/health smoke, diff checks, and the prior adversarial reproductions.
PR #72 remains Draft at this checkpoint. The next serialized action belongs to Maintainer Qy: leave Draft, re-read the final exact Head/Base/check/thread/mergeability gates, and squash merge only if every value remains stable.
Lifecycle remains unchanged until merge and merged-main CI:
Do not release #26 until PR #72 is squash-merged and the resulting main push quality-gate succeeds. Any PR code/head/base change invalidates the exact-head acceptance and requires a new complete Maintainer review.
The #25 Moss adapter port dependency is now satisfied. The single Builder execution slot moves to #26 for planning only. #23 remains Ready/unassigned, while #27 and later dependent issues remain Blocked until their own dependency and Scope Gates are satisfied.
This record does not authorize #26 implementation, Review, Merge Gate, or merge. Issue #26 must submit a closed Work Plan from exact main@a0f3a3e8605812c9f0997059b4a30ea7a736022c before implementation begins.
The first plan already closes many important decisions: an explicit 16-path writable set; one public adapter entry; canonical integer-string/BigInt amount handling; byte-stable protocol tie-breaking; per-protocol terminal outcomes; collector-local 8-second timeout and late-settlement drainage; timing exclusion from selection and digest; Quote-not-execution-evidence wording; and independently checked canonicalize@3.0.0 package metadata.
Four contract blockers remain before implementation can be authorized:
the caller-controlled request can self-assert MAINTAINER_APPROVED asset-catalog authority; the revised plan must separate untrusted request data from server-owned catalog configuration and freeze catalog identity/version/provenance/failure behavior;
candidate outcomes, normalized/timing/failure records, and selected/NOT_SELECTED top-level results are not yet exact discriminated unions, leaving contradictory optional-field combinations and failure precedence open;
the plan overclaims underlying source cancellation; it must distinguish collector terminality, signal propagation, and unverified source cancellation, and test cooperative plus signal-ignoring late fulfillment/rejection;
RFC 8785 acceptance evidence is not frozen to named published vectors, exact canonical UTF-8 output, and an exact project payload with expected lowercase SHA-256.
The next serialized action belongs to Builder Qy: leave the first plan and review unchanged as history, reconfirm the same main baseline, and submit one complete revised Work Plan restating the full path list, dependencies, API/port change, exact public contracts, catalog trust boundary, timeout semantics, digest/time rules, tests, non-goals, stop conditions, and requested decision.
Do not create the #26 branch, worktree, file change, dependency update, commit, push, or PR before a later Maintainer SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED record.
RFC dependency metadata and project/catalog digest vectors are independently stated.
Two exact blockers remain:
The exported INELIGIBLE union still permits contradictory combinations because its raw field accepts the entire RawQuoteRetentionV0_1 union. The public type therefore permits UNSNAPSHOTTABLE + ASSET_DIRECTION_MISMATCH and UNSNAPSHOTTABLE + AMOUNT_BASIS_MISMATCH, even though prose says only MALFORMED_QUOTE may be unsnapshottable. The revised type must use correlated branches that make invalid combinations unrepresentable, with compile-time/type-level and runtime evidence.
The RFC 8785 vector is internally inconsistent. The displayed canonical text contains the invalid JSON form \\^O, while the declared bytes and SHA encode the valid lowercase Unicode escape \\u000f. The next plan must use one valid canonical text and independently prove that its UTF-8 bytes, expected hex, canonicalize output, and SHA-256 are identical.
The next serialized action belongs to Builder Qy: keep v1 and v2 unchanged as audit history and submit one complete self-contained Work Plan v3 from the same main baseline, restating the full 16 paths, two dependencies, public contracts, catalog boundary, timeout semantics, exact correlated unions, corrected RFC vector, tests, non-goals, and stop conditions.
No #26 branch, worktree, dependency installation, lockfile generation, file change, commit, push, or PR is authorized until a later Maintainer SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED record.
The v2 correlated-union blocker is closed at plan level. V3 now has separate malformed, asset-direction-mismatch, and amount-basis-mismatch members, making both UNSNAPSHOTTABLE mismatch combinations unrepresentable. Its compile-time satisfies / AssertNever / @ts-expect-error evidence and runtime correlation matrix are acceptable. Previously accepted catalog, timeout, late-drainage, BigInt, digest, raw-evidence, Quote-not-execution-evidence, exact 16-path, exact two-dependency, and #27 isolation decisions remain intact.
One P0 RFC vector blocker remains. In the actual final v3 comment body, both JSON blocks encode the U+000F position as the three ASCII characters backslash-caret-O, hex 5c 5e 4f. That is not a valid JSON escape. The frozen expected byte vector instead uses the required six ASCII characters backslash-lowercase-u-000f, hex 5c 75 30 30 30 66. Consequently both displayed JSON blocks fail JSON.parse, their actual byte length and SHA differ from the declared 118-byte vector and 2d5e01a3... hash.
The next serialized action belongs to Builder Qy: preserve v1-v3 and all reviews as history, then submit one complete self-contained Work Plan v4. Both reference-input and canonical-output JSON blocks must contain the literal six ASCII bytes 5c 75 30 30 30 66, not caret notation and not an actual control byte. Before requesting review, re-fetch the posted GitHub comment and prove both JSON parses succeed, the decoded character is U+000F, canonical text is 118 UTF-8 bytes, hex matches the frozen vector, SHA-256 is 2d5e01a318d0f0879ab568c4be289c8b1f64ef8921a53c6277d5e069978baacb, and canonicalize@3.0.0 output equals the canonical text byte-for-byte.
Keep all accepted v3 decisions unchanged: the exact correlated unions, compile-time/runtime matrix, 16 paths, two dependencies, catalog boundary, timeout semantics, vectors outside the corrected RFC text, tests, non-goals, and stop conditions.
No #26 branch, worktree, dependency installation, lockfile generation, file change, commit, push, or PR is authorized until a later Maintainer SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED record.
The P0 RFC vector blocker is closed. Readback proves both JSON blocks parse, decode the intended U+000F value, produce the exact 118-byte canonical UTF-8 vector, match the frozen full hex, match SHA-256 2d5e01a318d0f0879ab568c4be289c8b1f64ef8921a53c6277d5e069978baacb, and match canonicalize@3.0.0 byte-for-byte. The correlated outcome unions, compile-time and runtime correlation matrix, exact 16 writable paths, exact two dependencies, catalog boundary, timeout and late-drainage semantics, BigInt comparison, digest contract, raw-evidence separation, Quote-not-execution-evidence boundary, #27 isolation, tests, non-goals, and stop conditions are accepted exactly as frozen in v4.
At this checkpoint there is no #26 implementation branch, worktree, commit, push, or pull request. Authorization is not implementation completion.
The next serialized action belongs to Builder Qy: re-fetch and verify the exact baseline, then create codex/issue-26-quote-selection in isolated worktree /Users/qy/Documents/moss-mini-demo-issue-26 and implement only the frozen v4 scope. If origin/main has moved, Builder must stop and request a revised Scope Gate before creating implementation changes.
The authorized writable-path count is now 17. The sole added path is packages/moss-adapter/test/server-only.test.ts, and its sole authorized semantic change is adding collectAndSelectQuotesV0_1 to the existing exact runtime-export allowlist in default JavaScript sort order.
Reason: frozen Work Plan v4 already requires that exact sole new runtime export and requires all existing server-only/full tests to remain green, while current main contains an independent closed export allowlist in this previously omitted test. This is a v4 writable-list correction, not a contract/version change.
All other v4 authority, two-dependency limit, #27 isolation, non-goals, tests, and stop conditions remain unchanged. Any eighteenth path or any second semantic change in the added test remains a stop condition.
PR head, reported frozen head, implementation commit, and CI head are identical;
exact changed-file count is 17;
all 17 paths match Work Plan v4 plus the approved path-17 amendment;
packages/moss-adapter/test/server-only.test.ts changes by exactly one allowlist insertion for collectAndSelectQuotesV0_1;
package manifest adds exactly @moss-mini-demo/report-schema: workspace:* and canonicalize: 3.0.0;
lockfile delta is limited to those importer/package records;
Builder reports Node 22.23.1 / pnpm 11.16.0, 102 adapter tests, 23 files / 792 full tests, package import, Web bundle, Web production, diff check, and exact path audit passing.
The next serialized action belongs to Maintainer Qy: independently review and reproduce the frozen exact head, with particular focus on fail-closed request/catalog boundaries, correlated outcomes, timeout and late-settlement drainage, raw evidence ownership, BigInt/UTF-8 ordering, frozen RFC/catalog/selected digest vectors, exact runtime exports, and #27 isolation.
Builder Qy must keep head 97e2806d43caae1881adae9b1c620a2b79d8ce84 frozen during review. Any head change invalidates current-head QA and requires a fresh exact-head CI and handoff.
proposed branch after authorization: codex/issue-27-capability-integrity
proposed isolated worktree after authorization: /Users/qy/Documents/moss-mini-demo-issue-27
The next serialized action belongs to Builder Qy: produce one closed, exact Work Plan for #27 covering writable paths, public/internal contracts, amount conversion, exact raw Capability identity, independent snapshot/digest, simulator identity handoff, mutation detection, dependencies, tests, non-goals, and stop conditions.
No #27 branch, worktree, code change, commit, push, dependency installation, or PR is authorized until a Maintainer SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED record is published.
The 15-path list, viem@2.55.11, BigInt-only amount boundary, #26 exclusion, and #28 isolation are directionally acceptable. Four P0 trust-boundary gaps must be resolved in a replacement Work Plan:
MAINTAINER_APPROVED address metadata is caller-asserted without an authority-backed tracked record or a synthetic-only fail-closed contract.
Builder must preserve v1 as history and submit a complete self-contained Work Plan v2 resolving all four items. Do not edit v1 in place. Until a new Maintainer SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED record exists:
V2 resolves the prior production-authority, authoritative-snapshot, #26 digest-helper reuse, exact path/dependency and #28 isolation blockers. One P0 descriptor-closure blocker remains.
The planned registered exact-input validator only closes own enumerable data values. The exact object forwarded to the simulator may still expose non-enumerable own data, Symbol keys, sparse arrays, or extra non-index array properties that RFC 8785/JSON evidence can omit or normalize. The simulator could therefore observe state not represented by a reported MATCH digest.
Builder must preserve v1 and v2 as history and publish a complete immutable Work Plan v3 requiring one shared JSON-exact validator for integrity verification and exact-identity simulate delegation. It must use trap-safe Reflect.ownKeys, enforce closed record descriptors, enforce dense canonical arrays, reject descriptor violations, and add the exact non-enumerable/Symbol/sparse-array/extra-array-property regression matrix. The 15-path and dependency set may remain unchanged if sufficient.
Until a new Maintainer SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED record exists:
Lifecycle remains #27 Open / Qy assigned / Project In Progress for planning only. This checkpoint is not implementation authorization, QA PASS, Review, READY_TO_MERGE, Merge Gate, or merge authorization.
Issue #27 is now implementation-authorized with exactly 15 writable paths, sole direct dependency viem@2.55.11, sole new runtime export constructCapabilityV0_1, and only the two named type exports.
Frozen requirements include synthetic-only policy, reuse of #26's authoritative source-boundary snapshot and createSelectedQuoteDigest, one shared JSON-exact descriptor validator for integrity and registered simulate input, synchronous exact-identity delegation after validation, the four descriptor regression cases, and strict #28 isolation.
publish Implementation Report and Pre-PR QA Handoff;
freeze the exact head.
No #27 implementation branch, worktree, file change, commit, push, or PR existed at this checkpoint. Authorization is not QA PASS or merge authorization.
The delivery matches the 15-path, sole viem@2.55.11, sole runtime-export and #28-isolation boundaries, and all reported/local/CI tests are green. Maintainer review nevertheless found four P1 frozen-contract defects:
capability construction re-applies catalog freshness through Date.now(), breaking offline determinism and returning INVALID_INPUT / quote instead of the action boundary;
selected Quote and action evidence build identities are not associated;
a shallow-frozen forged snapshot is accepted without proving deep immutability;
caller-controlled repeated object aliases are accepted even though v3 requires rejection before action delegation.
The next serialized action belongs to Builder Qy: fix all four defects within the existing authorized 15 paths, add exact regressions, run the complete Node 22.23.1 / pnpm 11.16.0 matrix, push a new head, wait for new exact-head CI, publish a replacement Implementation Report and QA Handoff, then freeze the new head.
No Scope expansion is currently authorized or required. If the repeated-alias requirement cannot be met without weakening/changing the frozen contract, Builder must stop and request a replacement Scope Gate rather than silently changing semantics.
PR #74 remains Draft and is not authorized for READY_TO_MERGE or merge. #28 remains Blocked; #23 remains Ready/unassigned.
BATCH_A / M2 COMPLETE: all 13 child Issues are Closed/Completed and Project Done; non-UI Gate PASS; main 41a32cabd12702fa4786bdf72160db381fa6f542; quality-gate run 31248130228 SUCCESS; zero open PRs.
Activity
11 remaining items
pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_25_READY_TO_MERGE_CHECKPOINT
Current main remains
1e42babfa457ad20ac1efcecca227aceb4995c2b; merged-mainquality-gaterun30999528946remains successful.PR #72 is the sole open pull request and has passed complete current-head Maintainer review:
1b45d53e8307b579a6840b01e472f03d896867e3main@1e42babfa457ad20ac1efcecca227aceb4995c2bquality-gate: SUCCESS, https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/31069505170/job/92514274448Both prior trust-boundary findings are closed. Independent Node
22.23.1/ pnpm11.16.0Maintainer verification passed adapter build/typecheck, 5 adapter files / 38 tests, public package import, fullpnpm checkwith 21 files / 728 tests, browser bundle scan, production start/health smoke, diff checks, and the prior adversarial reproductions.PR #72 remains Draft at this checkpoint. The next serialized action belongs to Maintainer Qy: leave Draft, re-read the final exact Head/Base/check/thread/mergeability gates, and squash merge only if every value remains stable.
Lifecycle remains unchanged until merge and merged-main CI:
Do not release #26 until PR #72 is squash-merged and the resulting
mainpushquality-gatesucceeds. Any PR code/head/base change invalidates the exact-head acceptance and requires a new complete Maintainer review.pillowtalk-Qy commentedon Aug 6, 2026
M2_EXECUTION_BASELINE_UPDATE - post-#25 merge
Issue #25 was completed through PR #72: #72
1b45d53e8307b579a6840b01e472f03d896867e3main@1e42babfa457ad20ac1efcecca227aceb4995c2ba0f3a3e8605812c9f0997059b4a30ea7a736022c2026-08-06T04:13:31ZThe #25 Moss adapter port dependency is now satisfied. The single Builder execution slot moves to #26 for planning only. #23 remains Ready/unassigned, while #27 and later dependent issues remain Blocked until their own dependency and Scope Gates are satisfied.
This record does not authorize #26 implementation, Review, Merge Gate, or merge. Issue #26 must submit a closed Work Plan from exact
main@a0f3a3e8605812c9f0997059b4a30ea7a736022cbefore implementation begins.pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_26_SCOPE_CHANGES_REQUESTED_CHECKPOINT
Current main remains
a0f3a3e8605812c9f0997059b4a30ea7a736022c; merged-mainquality-gaterun31070657110remains successful.Issue #26 planning has entered its first Scope Gate:
SCOPE_CHANGES_REQUESTED: M2-05: Implement quote collection and deterministic selection #26 (comment)The first plan already closes many important decisions: an explicit 16-path writable set; one public adapter entry; canonical integer-string/BigInt amount handling; byte-stable protocol tie-breaking; per-protocol terminal outcomes; collector-local 8-second timeout and late-settlement drainage; timing exclusion from selection and digest; Quote-not-execution-evidence wording; and independently checked
canonicalize@3.0.0package metadata.Four contract blockers remain before implementation can be authorized:
MAINTAINER_APPROVEDasset-catalog authority; the revised plan must separate untrusted request data from server-owned catalog configuration and freeze catalog identity/version/provenance/failure behavior;NOT_SELECTEDtop-level results are not yet exact discriminated unions, leaving contradictory optional-field combinations and failure precedence open;The next serialized action belongs to Builder Qy: leave the first plan and review unchanged as history, reconfirm the same main baseline, and submit one complete revised Work Plan restating the full path list, dependencies, API/port change, exact public contracts, catalog trust boundary, timeout semantics, digest/time rules, tests, non-goals, stop conditions, and requested decision.
Lifecycle remains unchanged:
Do not create the #26 branch, worktree, file change, dependency update, commit, push, or PR before a later Maintainer
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZEDrecord.pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_26_SCOPE_V2_CHANGES_REQUESTED_CHECKPOINT
Current main remains
a0f3a3e8605812c9f0997059b4a30ea7a736022c; merged-mainquality-gaterun31070657110remains successful.Issue #26 Work Plan v2 was submitted and independently reviewed:
Work Plan v2 correctly resolved the prior four blockers:
Two exact blockers remain:
The exported
INELIGIBLEunion still permits contradictory combinations because itsrawfield accepts the entireRawQuoteRetentionV0_1union. The public type therefore permitsUNSNAPSHOTTABLE + ASSET_DIRECTION_MISMATCHandUNSNAPSHOTTABLE + AMOUNT_BASIS_MISMATCH, even though prose says onlyMALFORMED_QUOTEmay be unsnapshottable. The revised type must use correlated branches that make invalid combinations unrepresentable, with compile-time/type-level and runtime evidence.The RFC 8785 vector is internally inconsistent. The displayed canonical text contains the invalid JSON form
\\^O, while the declared bytes and SHA encode the valid lowercase Unicode escape\\u000f. The next plan must use one valid canonical text and independently prove that its UTF-8 bytes, expected hex, canonicalize output, and SHA-256 are identical.The next serialized action belongs to Builder Qy: keep v1 and v2 unchanged as audit history and submit one complete self-contained Work Plan v3 from the same main baseline, restating the full 16 paths, two dependencies, public contracts, catalog boundary, timeout semantics, exact correlated unions, corrected RFC vector, tests, non-goals, and stop conditions.
Lifecycle remains unchanged:
No #26 branch, worktree, dependency installation, lockfile generation, file change, commit, push, or PR is authorized until a later Maintainer
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZEDrecord.pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_26_SCOPE_V3_CHANGES_REQUESTED_CHECKPOINT
Current main remains
a0f3a3e8605812c9f0997059b4a30ea7a736022c; merged-mainquality-gaterun31070657110remains successful.Issue #26 Work Plan v3 was submitted, edited to its frozen review object, and reviewed:
2026-08-06T05:58:07ZThe v2 correlated-union blocker is closed at plan level. V3 now has separate malformed, asset-direction-mismatch, and amount-basis-mismatch members, making both
UNSNAPSHOTTABLEmismatch combinations unrepresentable. Its compile-timesatisfies/AssertNever/@ts-expect-errorevidence and runtime correlation matrix are acceptable. Previously accepted catalog, timeout, late-drainage, BigInt, digest, raw-evidence, Quote-not-execution-evidence, exact 16-path, exact two-dependency, and #27 isolation decisions remain intact.One P0 RFC vector blocker remains. In the actual final v3 comment body, both JSON blocks encode the U+000F position as the three ASCII characters backslash-caret-O, hex
5c 5e 4f. That is not a valid JSON escape. The frozen expected byte vector instead uses the required six ASCII characters backslash-lowercase-u-000f, hex5c 75 30 30 30 66. Consequently both displayed JSON blocks failJSON.parse, their actual byte length and SHA differ from the declared 118-byte vector and2d5e01a3...hash.The next serialized action belongs to Builder Qy: preserve v1-v3 and all reviews as history, then submit one complete self-contained Work Plan v4. Both reference-input and canonical-output JSON blocks must contain the literal six ASCII bytes
5c 75 30 30 30 66, not caret notation and not an actual control byte. Before requesting review, re-fetch the posted GitHub comment and prove both JSON parses succeed, the decoded character is U+000F, canonical text is 118 UTF-8 bytes, hex matches the frozen vector, SHA-256 is2d5e01a318d0f0879ab568c4be289c8b1f64ef8921a53c6277d5e069978baacb, andcanonicalize@3.0.0output equals the canonical text byte-for-byte.Keep all accepted v3 decisions unchanged: the exact correlated unions, compile-time/runtime matrix, 16 paths, two dependencies, catalog boundary, timeout semantics, vectors outside the corrected RFC text, tests, non-goals, and stop conditions.
Lifecycle remains unchanged:
No #26 branch, worktree, dependency installation, lockfile generation, file change, commit, push, or PR is authorized until a later Maintainer
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZEDrecord.pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_26_SCOPE_V4_AUTHORIZED_CHECKPOINT
Current remote main remains
a0f3a3e8605812c9f0997059b4a30ea7a736022c(feat: add Moss adapter ports (#72)); merged-mainquality-gaterun31070657110remains successful:https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/31070657110
Issue #26 Work Plan v4 has completed publication readback and the Maintainer Scope Gate:
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED: M2-05: Implement quote collection and deterministic selection #26 (comment)Frozen v4 authority:
5201269230updated_at:2026-08-06T06:42:10Zf30f88dbe065a257a669d5c68e9f50abb7ae0495bd9232d7a69e5525a7322732origin/main@a0f3a3e8605812c9f0997059b4a30ea7a736022cThe P0 RFC vector blocker is closed. Readback proves both JSON blocks parse, decode the intended U+000F value, produce the exact 118-byte canonical UTF-8 vector, match the frozen full hex, match SHA-256
2d5e01a318d0f0879ab568c4be289c8b1f64ef8921a53c6277d5e069978baacb, and matchcanonicalize@3.0.0byte-for-byte. The correlated outcome unions, compile-time and runtime correlation matrix, exact 16 writable paths, exact two dependencies, catalog boundary, timeout and late-drainage semantics, BigInt comparison, digest contract, raw-evidence separation, Quote-not-execution-evidence boundary, #27 isolation, tests, non-goals, and stop conditions are accepted exactly as frozen in v4.At this checkpoint there is no #26 implementation branch, worktree, commit, push, or pull request. Authorization is not implementation completion.
The next serialized action belongs to Builder Qy: re-fetch and verify the exact baseline, then create
codex/issue-26-quote-selectionin isolated worktree/Users/qy/Documents/moss-mini-demo-issue-26and implement only the frozen v4 scope. Iforigin/mainhas moved, Builder must stop and request a revised Scope Gate before creating implementation changes.Lifecycle remains:
This checkpoint is not Implementation Report, QA PASS, Review, READY_TO_MERGE, Merge Gate, or merge authorization.
pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_26_SCOPE_AMENDMENT_PATH_17_CHECKPOINT
Maintainer approved one closed Scope Amendment for Issue #26:
#26 (comment)
The authorized writable-path count is now 17. The sole added path is
packages/moss-adapter/test/server-only.test.ts, and its sole authorized semantic change is addingcollectAndSelectQuotesV0_1to the existing exact runtime-export allowlist in default JavaScript sort order.Reason: frozen Work Plan v4 already requires that exact sole new runtime export and requires all existing server-only/full tests to remain green, while current main contains an independent closed export allowlist in this previously omitted test. This is a v4 writable-list correction, not a contract/version change.
All other v4 authority, two-dependency limit, #27 isolation, non-goals, tests, and stop conditions remain unchanged. Any eighteenth path or any second semantic change in the added test remains a stop condition.
Lifecycle remains unchanged:
This checkpoint is not QA PASS, READY_TO_MERGE, Merge Gate, or merge authorization.
pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_26_IMPLEMENTATION_HANDOFF_CHECKPOINT
Issue #26 implementation has reached the independent Pre-PR QA gate.
Frozen review object:
main@a0f3a3e8605812c9f0997059b4a30ea7a736022c97e2806d43caae1881adae9b1c620a2b79d8ce84quality-gate: SUCCESSMaintainer preflight verification confirms:
packages/moss-adapter/test/server-only.test.tschanges by exactly one allowlist insertion forcollectAndSelectQuotesV0_1;@moss-mini-demo/report-schema: workspace:*andcanonicalize: 3.0.0;22.23.1/ pnpm11.16.0, 102 adapter tests, 23 files / 792 full tests, package import, Web bundle, Web production, diff check, and exact path audit passing.The next serialized action belongs to Maintainer Qy: independently review and reproduce the frozen exact head, with particular focus on fail-closed request/catalog boundaries, correlated outcomes, timeout and late-settlement drainage, raw evidence ownership, BigInt/UTF-8 ordering, frozen RFC/catalog/selected digest vectors, exact runtime exports, and #27 isolation.
Builder Qy must keep head
97e2806d43caae1881adae9b1c620a2b79d8ce84frozen during review. Any head change invalidates current-head QA and requires a fresh exact-head CI and handoff.Lifecycle remains unchanged:
This checkpoint is not QA PASS, Review approval, READY_TO_MERGE, Merge Gate, or merge authorization.
pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_26_COMPLETE_ISSUE_27_PLANNING_SLOT_CHECKPOINT
Issue #26 has completed its full lifecycle:
97e2806d43caae1881adae9b1c620a2b79d8ce8465753ada85156716e263b660eeab72c42d293431quality-gate: SUCCESSM2 now records 5 closed items and 9 open items.
Issue #27 dependency gate is cleared and the single active P0 planning slot is assigned to Builder Qy:
origin/main@65753ada85156716e263b660eeab72c42d293431codex/issue-27-capability-integrity/Users/qy/Documents/moss-mini-demo-issue-27The next serialized action belongs to Builder Qy: produce one closed, exact Work Plan for #27 covering writable paths, public/internal contracts, amount conversion, exact raw Capability identity, independent snapshot/digest, simulator identity handoff, mutation detection, dependencies, tests, non-goals, and stop conditions.
No #27 branch, worktree, code change, commit, push, dependency installation, or PR is authorized until a Maintainer
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZEDrecord is published.Lifecycle:
This checkpoint is not #27 Scope Confirmation, implementation authorization, QA PASS, Review, READY_TO_MERGE, Merge Gate, or merge authorization.
pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_27_SCOPE_V1_REJECTED_CHECKPOINT
Issue #27 Work Plan v1 was reviewed and is not authorized for implementation.
Scope decision:
#27 (comment)
The 15-path list,
viem@2.55.11, BigInt-only amount boundary, #26 exclusion, and #28 isolation are directionally acceptable. Four P0 trust-boundary gaps must be resolved in a replacement Work Plan:MAINTAINER_APPROVEDaddress metadata is caller-asserted without an authority-backed tracked record or a synthetic-only fail-closed contract.MossPort.actionreturns.Builder must preserve v1 as history and submit a complete self-contained Work Plan v2 resolving all four items. Do not edit v1 in place. Until a new Maintainer
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZEDrecord exists:Current lifecycle:
This checkpoint is not implementation authorization, QA PASS, Review, READY_TO_MERGE, Merge Gate, or merge authorization.
pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_27_SCOPE_V2_REJECTED_CHECKPOINT
Issue #27 Work Plan v2 was reviewed and is not authorized for implementation.
52060534382026-08-06T14:30:42Zc70046d4df0734e6ea99ee8fbb3b075a385c171d68e626da556c4d8114cde7b165753ada85156716e263b660eeab72c42d293431V2 resolves the prior production-authority, authoritative-snapshot, #26 digest-helper reuse, exact path/dependency and #28 isolation blockers. One P0 descriptor-closure blocker remains.
The planned registered exact-input validator only closes own enumerable data values. The exact object forwarded to the simulator may still expose non-enumerable own data, Symbol keys, sparse arrays, or extra non-index array properties that RFC 8785/JSON evidence can omit or normalize. The simulator could therefore observe state not represented by a reported MATCH digest.
Builder must preserve v1 and v2 as history and publish a complete immutable Work Plan v3 requiring one shared JSON-exact validator for integrity verification and exact-identity simulate delegation. It must use trap-safe
Reflect.ownKeys, enforce closed record descriptors, enforce dense canonical arrays, reject descriptor violations, and add the exact non-enumerable/Symbol/sparse-array/extra-array-property regression matrix. The 15-path and dependency set may remain unchanged if sufficient.Until a new Maintainer
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZEDrecord exists:Lifecycle remains #27 Open / Qy assigned / Project In Progress for planning only. This checkpoint is not implementation authorization, QA PASS, Review, READY_TO_MERGE, Merge Gate, or merge authorization.
pillowtalk-Qy commentedon Aug 6, 2026
ISSUE_27_SCOPE_V3_AUTHORIZED_CHECKPOINT
Issue #27 Work Plan v3 has passed the Maintainer Scope Gate.
52063743842026-08-06T14:51:21Zd53b3d458640286079fae2ad4eabf0f39b702a97ab7ff48487feedb6b0d6a766origin/main@65753ada85156716e263b660eeab72c42d293431Issue #27 is now implementation-authorized with exactly 15 writable paths, sole direct dependency
viem@2.55.11, sole new runtime exportconstructCapabilityV0_1, and only the two named type exports.Frozen requirements include synthetic-only policy, reuse of #26's authoritative source-boundary snapshot and
createSelectedQuoteDigest, one shared JSON-exact descriptor validator for integrity and registered simulate input, synchronous exact-identity delegation after validation, the four descriptor regression cases, and strict #28 isolation.The next serialized action belongs to Builder Qy:
codex/issue-27-capability-integrity;/Users/qy/Documents/moss-mini-demo-issue-27;viem@2.55.11;Closes #27;No #27 implementation branch, worktree, file change, commit, push, or PR existed at this checkpoint. Authorization is not QA PASS or merge authorization.
Lifecycle remains:
pillowtalk-Qy commentedon Aug 7, 2026
ISSUE_27_PR74_CHANGES_REQUESTED_CHECKPOINT
Issue #27 implementation reached Draft PR and exact-head review:
main@65753ada85156716e263b660eeab72c42d2934311362b60539cd36932d73708d0bf632475e71b966The delivery matches the 15-path, sole
viem@2.55.11, sole runtime-export and #28-isolation boundaries, and all reported/local/CI tests are green. Maintainer review nevertheless found four P1 frozen-contract defects:Date.now(), breaking offline determinism and returningINVALID_INPUT / quoteinstead of the action boundary;The next serialized action belongs to Builder Qy: fix all four defects within the existing authorized 15 paths, add exact regressions, run the complete Node
22.23.1/ pnpm11.16.0matrix, push a new head, wait for new exact-head CI, publish a replacement Implementation Report and QA Handoff, then freeze the new head.No Scope expansion is currently authorized or required. If the repeated-alias requirement cannot be met without weakening/changing the frozen contract, Builder must stop and request a replacement Scope Gate rather than silently changing semantics.
PR #74 remains Draft and is not authorized for READY_TO_MERGE or merge. #28 remains Blocked; #23 remains Ready/unassigned.
pillowtalk-Qy commentedon Aug 8, 2026
BATCH_A / M2 COMPLETE: all 13 child Issues are Closed/Completed and Project Done; non-UI Gate PASS; main
41a32cabd12702fa4786bdf72160db381fa6f542; quality-gate run 31248130228 SUCCESS; zero open PRs.