M1-03: Implement fail-closed decision engine #6 is the next execution channel. Its Schema dependency gate is satisfied and implementation starts from the current main baseline through a detailed Contributor or Builder Work Plan.
Tracker M1-00: Evidence Contract Delivery Tracker #4 remains Open / Project In Progress. M1 has not reached its closure conditions, and this record does not close the tracker or set it to Done.
The M1 Milestone remains Open and overdue with its original 2026-07-24 due date. No new schedule is set until #6 Work Plan and initial implementation produce a credible estimate.
Accordingly, #6, #8, and #9 are now Project Blocked until their recorded dependencies are satisfied. Existing completed work (#5 and #7), merged ADRs, PR evidence, and the original overdue date are preserved.
This is a planning/dependency update. It does not accept #18, pass a Gate, authorize a merge, or close this tracker.
No new M1 target date is asserted. A credible recovery target requires the approved #6 Work Plan and initial implementation estimate. This update does not start #8/#20, pass M1, or close this tracker.
Issue #6 Work Plan v2 received SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED from exact main@7bbbc8bb9b4acb859bc73ba2b861f657864cce5c and has moved to Project In Progress.
This records implementation-scope authorization only. It is not QA PASS, GitHub Approval, READY_TO_MERGE, Merge Gate, or merge authorization. #8, #20, and #9 remain Blocked.
frozen-lockfile install and pnpm check passed in the GitHub clean checkout;
report-schema public package import passed;
8 test files / 340 tests passed / 0 failed.
This is baseline evidence only. It is not the final M1 closure gate because the required Decision Engine and two STOP Fixtures are not yet merged into main.
Current main documentation risk-term hits are limitation statements, not capability claims.
main protection still requires strict quality-gate, resolved conversations and linear history; enforce-admins is enabled, force push/delete are disabled, and push access remains restricted to the Maintainers Team.
The Decision Engine public package import and complete 22-code matrix are not present on current main.
The tokenOut and amountIn STOP Fixtures are not present. The required three-Fixture final validation therefore cannot pass.
The M1 closeout document is not delivered. Current README and real-vs-mock correctly state that there is no Decision Engine or STOP Fixture, confirming that this baseline is not closure-ready.
A final independent clean-main closure verification is withheld until the missing deliverables are merged; current CI results cannot be presented as evidence for absent components.
Tracker #4 remains Open / Project In Progress.
M1 Milestone remains Open.
No M2 handoff baseline is issued by this assessment.
No M2 implementation is authorized by this assessment.
Current serial order: #8 -> #20 -> #9 -> Tracker #4 closure assessment.
Qy may work on only one Fixture issue at a time. #20 remains unclaimed while #8 is In Progress. No implementation, branch, PR, Review, Merge Gate, or merge is authorized by this status record.
The repository has zero open pull requests, so there is no open M1 PR.
A fresh clean checkout of the exact main SHA passed with Node 22.23.1 and pnpm 11.16.0.
pnpm install --frozen-lockfile passed.
pnpm check passed: format, lint, typecheck, ordered builds, both public package-name import smoke tests, and 13 test files / 655 tests.
manual-review-success.v0.1.json validates as provenance: FIXTURE and the public Decision Engine recomputes {"status":"MANUAL_REVIEW"}.
token-out-mismatch.v0.1.json validates as provenance: FIXTURE and recomputes the exact CRITICAL_ALIGNMENT_FAIL STOP with its two raw-owned references.
amount-in-mismatch.v0.1.json validates as provenance: FIXTURE and recomputes the exact CRITICAL_ALIGNMENT_FAIL STOP with its three raw-owned references.
README, Real-versus-Mock, the M1 completion inventory, security-boundary, and Fixture documentation continue to separate synthetic evidence from live evidence and explicitly reject safety, approval, authorization, execution-guarantee, signing-permission, product, and real-chain claims.
Main protection remains strict: required quality-gate, strict up-to-date checks, resolved conversations, linear history, enforce admins, no force push or deletion, and push restriction to the Maintainers Team.
Conclusion: M1 satisfies the recorded closure criteria on the exact main baseline above.
Tracker #4 may be closed as Completed / Project Done and the M1 Milestone may be closed. This assessment does not itself implement M2 or authorize any M2 Issue beyond the separate post-closure execution-slot update.
Activity
[-]M1-02: Freeze PreflightReport v0.1 evidence contract and fail-closed fixtures[/-][+]M1-00: Evidence Contract Delivery Tracker[/+]15 remaining items
docs: accept PreflightReport v0.1 schema contract (#13)
pillowtalk-Qy commentedon Jul 25, 2026
M1 status update: ADR prerequisite completed; #5 implementation started
pillowtalk-Qy commentedon Jul 26, 2026
M1 status update: Decision Engine contract accepted
29d2cbcbb815eee81f16773b1487991386303c60pillowtalk-Qy commentedon Jul 27, 2026
Maintainer M1 post-PR #15 status
Current M1 baseline:
main@a210d9c297ddef4b42648b2c1343da5b9c19a407.Evidence:
quality-gateis SUCCESS: https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/30263166240/job/89967568066Control-plane status:
Execution order remains: #6/#7 -> #8 -> #9 -> Tracker #4 closure assessment.
pillowtalk-Qy commentedon Jul 27, 2026
Maintainer M1 post-PR #16 status
Current M1 baseline:
main@316dd1478b46185df862be80499963e42d73855b.Evidence:
quality-gateis SUCCESS: https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/30277600027/job/90015494282Control-plane status:
The M1 Milestone remains Open and overdue with its original 2026-07-24 due date. No new schedule is set until #6 Work Plan and initial implementation produce a credible estimate.
pillowtalk-Qy commentedon Jul 29, 2026
Hackathon recovery planning sync - 2026-07-29
Recovery target: 2026-07-29 23:00 Asia/Hong_Kong. The original M1 due date remains unchanged as historical fact.
New outstanding dependency chain:
Accordingly, #6, #8, and #9 are now Project Blocked until their recorded dependencies are satisfied. Existing completed work (#5 and #7), merged ADRs, PR evidence, and the original overdue date are preserved.
This is a planning/dependency update. It does not accept #18, pass a Gate, authorize a merge, or close this tracker.
pillowtalk-Qy commentedon Jul 31, 2026
M1 dependency and release sync - 2026-07-31
Current baseline:
main@27a9bc66f483a25d6602fdac2748099bfb32d67e.Completed dependency evidence:
Current control state:
status:ready/ Project Ready and remains assigned to @pillowtalk-Qy.Corrected release chain:
No new M1 target date is asserted. A credible recovery target requires the approved #6 Work Plan and initial implementation estimate. This update does not start #8/#20, pass M1, or close this tracker.
pillowtalk-Qy commentedon Aug 2, 2026
Issue #6 implementation-scope authorization index
Issue #6 Work Plan v2 received
SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZEDfrom exactmain@7bbbc8bb9b4acb859bc73ba2b861f657864cce5cand has moved to Project In Progress.This records implementation-scope authorization only. It is not QA PASS, GitHub Approval, READY_TO_MERGE, Merge Gate, or merge authorization. #8, #20, and #9 remain Blocked.
pillowtalk-Qy commentedon Aug 3, 2026
M1_CLOSURE_NOT_READY
Evaluated
main@7bbbc8bb9b4acb859bc73ba2b861f657864cce5c.Current main push quality-gate: SUCCESS
https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/30752494660/job/91508902082
Current-baseline quality evidence:
v22.23.1and pnpm11.16.0;pnpm checkpassed in the GitHub clean checkout;This is baseline evidence only. It is not the final M1 closure gate because the required Decision Engine and two STOP Fixtures are not yet merged into main.
Completed:
edd37e0b977fe2821752dda4d4c3b4715238ffe8.a210d9c297ddef4b42648b2c1343da5b9c19a407.316dd1478b46185df862be80499963e42d73855b.27a9bc66f483a25d6602fdac2748099bfb32d67e.main@7bbbc8bb9b4acb859bc73ba2b861f657864cce5c.quality-gate, resolved conversations and linear history; enforce-admins is enabled, force push/delete are disabled, and push access remains restricted to the Maintainers Team.Outstanding:
5d4731985beb86281610ca7abf187287e5b1d8a0onmain@7bbbc8bb9b4acb859bc73ba2b861f657864cce5c. Its exact-head CI is SUCCESS, but the QA handoff remains incomplete and no Maintainer squash merge or merged-main CI exists.status:blocked/ Project Blocked, with no closing implementation PR or merge commit.status:blocked/ Project Blocked, with no closing implementation PR or merge commit.status:blocked/ Project Blocked, with no closeout PR or merge commit.5open issues: M1-00: Evidence Contract Delivery Tracker #4, M1-03: Implement fail-closed decision engine #6, M1-05: Add tokenOut mismatch STOP fixture #8, M1-06: Document M1 evidence boundary and completion criteria #9 and M1-09: Add amountIn mismatch STOP fixture #20. The historical due date remains 2026-07-24.Tracker #4 remains Open / Project In Progress.
M1 Milestone remains Open.
No M2 handoff baseline is issued by this assessment.
No M2 implementation is authorized by this assessment.
pillowtalk-Qy commentedon Aug 3, 2026
POST_ISSUE_6_EXECUTION_INDEX
Merged baseline:
main@aa7ea761b2ac5e78535387e0a7d04d45485cdfb1Merged-main
pushquality-gate: SUCCESS, https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/30833497929/job/91752910028Current M1 execution state:
status:ready/ Project Readystatus:blocked/ Project BlockedCurrent serial order: #8 -> #20 -> #9 -> Tracker #4 closure assessment.
Qy may work on only one Fixture issue at a time. #20 remains unclaimed while #8 is In Progress. No implementation, branch, PR, Review, Merge Gate, or merge is authorized by this status record.
pillowtalk-Qy commentedon Aug 5, 2026
M1_CLOSURE_PASS
Assessment baseline:
main@aae0397da1ba4924422d5a456123e9a4243b1797Merged-main evidence:
aae0397da1ba4924422d5a456123e9a4243b1797Independent Maintainer closure assessment:
22.23.1and pnpm11.16.0.pnpm install --frozen-lockfilepassed.pnpm checkpassed: format, lint, typecheck, ordered builds, both public package-name import smoke tests, and 13 test files / 655 tests.manual-review-success.v0.1.jsonvalidates asprovenance: FIXTUREand the public Decision Engine recomputes{"status":"MANUAL_REVIEW"}.token-out-mismatch.v0.1.jsonvalidates asprovenance: FIXTUREand recomputes the exactCRITICAL_ALIGNMENT_FAILSTOP with its two raw-owned references.amount-in-mismatch.v0.1.jsonvalidates asprovenance: FIXTUREand recomputes the exactCRITICAL_ALIGNMENT_FAILSTOP with its three raw-owned references.quality-gate, strict up-to-date checks, resolved conversations, linear history, enforce admins, no force push or deletion, and push restriction to the Maintainers Team.Conclusion: M1 satisfies the recorded closure criteria on the exact main baseline above.
Tracker #4 may be closed as Completed / Project Done and the M1 Milestone may be closed. This assessment does not itself implement M2 or authorize any M2 Issue beyond the separate post-closure execution-slot update.