M1-00: Evidence Contract Delivery Tracker #4

Closed
8 of 8 issues completed
Closed

Description

@pillowtalk-Qy

角色:父级 Delivery Tracker,仅管理 M1 Evidence Contract 的发布顺序、原生 Sub-issues 与完成条件;不包含业务代码。

协作方式:
Issue 可以立即认领和开发。发布顺序仅约束合并,
不限制调研、分支、Draft PR 或测试工作。

发布顺序:

  1. M1-01: Initialize TypeScript workspace and quality-gate CI #3 M1-01 CI
  2. M1-02: Define PreflightReport v0.1 runtime schema #5 M1-02 Schema
  3. M1-03: Implement fail-closed decision engine #6 M1-03 Decision Engine 与 M1-04: Add MANUAL_REVIEW success fixture #7 M1-04 Success Fixture
  4. M1-05: Add tokenOut mismatch STOP fixture #8 M1-05 STOP Fixture
  5. M1-06: Document M1 evidence boundary and completion criteria #9 M1-06 Documentation
  6. M1-00: Evidence Contract Delivery Tracker #4 M1-00 Tracker closure

M1 完成条件:

不设置具体执行时点;Milestone 截止日期为 2026-07-24。

Activity

  1. added
    type:choreRepository maintenance
    and removed
    type:featureNew product functionality
    area:qaQuality assurance and testing
    on Jul 22, 2026
  2. changed the title [-]M1-02: Freeze PreflightReport v0.1 evidence contract and fail-closed fixtures[/-] [+]M1-00: Evidence Contract Delivery Tracker[/+] on Jul 22, 2026
  3. 15 remaining items

  4. pillowtalk-Qy commented on Jul 25, 2026

    @pillowtalk-Qy
    ContributorAuthor

    M1 status update: ADR prerequisite completed; #5 implementation started

  5. pillowtalk-Qy commented on Jul 26, 2026

    @pillowtalk-Qy
    ContributorAuthor

    M1 status update: Decision Engine contract accepted

  6. pillowtalk-Qy commented on Jul 27, 2026

    @pillowtalk-Qy
    ContributorAuthor

    Maintainer M1 post-PR #15 status

    Current M1 baseline: main@a210d9c297ddef4b42648b2c1343da5b9c19a407.

    Evidence:

    Control-plane status:

    Execution order remains: #6/#7 -> #8 -> #9 -> Tracker #4 closure assessment.

  7. pillowtalk-Qy commented on Jul 27, 2026

    @pillowtalk-Qy
    ContributorAuthor

    Maintainer M1 post-PR #16 status

    Current M1 baseline: main@316dd1478b46185df862be80499963e42d73855b.

    Evidence:

    Control-plane status:

    The M1 Milestone remains Open and overdue with its original 2026-07-24 due date. No new schedule is set until #6 Work Plan and initial implementation produce a credible estimate.

  8. pillowtalk-Qy commented on Jul 29, 2026

    @pillowtalk-Qy
    ContributorAuthor

    Hackathon recovery planning sync - 2026-07-29

    Recovery target: 2026-07-29 23:00 Asia/Hong_Kong. The original M1 due date remains unchanged as historical fact.

    New outstanding dependency chain:

    Accordingly, #6, #8, and #9 are now Project Blocked until their recorded dependencies are satisfied. Existing completed work (#5 and #7), merged ADRs, PR evidence, and the original overdue date are preserved.

    This is a planning/dependency update. It does not accept #18, pass a Gate, authorize a merge, or close this tracker.

  9. pillowtalk-Qy commented on Jul 31, 2026

    @pillowtalk-Qy
    ContributorAuthor

    M1 dependency and release sync - 2026-07-31

    Current baseline: main@27a9bc66f483a25d6602fdac2748099bfb32d67e.

    Completed dependency evidence:

    Current control state:

    Corrected release chain:

    #6
      -> #8 tokenOut fixture + #20 amountIn fixture (parallel development, serialized rebase/merge)
      -> #9 M1 evidence closeout
      -> #4 closure assessment + exact main quality-gate
    

    No new M1 target date is asserted. A credible recovery target requires the approved #6 Work Plan and initial implementation estimate. This update does not start #8/#20, pass M1, or close this tracker.

  10. pillowtalk-Qy commented on Aug 2, 2026

    @pillowtalk-Qy
    ContributorAuthor

    Issue #6 implementation-scope authorization index

    Issue #6 Work Plan v2 received SCOPE_CONFIRMED / IMPLEMENTATION_AUTHORIZED from exact main@7bbbc8bb9b4acb859bc73ba2b861f657864cce5c and has moved to Project In Progress.

    This records implementation-scope authorization only. It is not QA PASS, GitHub Approval, READY_TO_MERGE, Merge Gate, or merge authorization. #8, #20, and #9 remain Blocked.

  11. pillowtalk-Qy commented on Aug 3, 2026

    @pillowtalk-Qy
    ContributorAuthor

    M1_CLOSURE_NOT_READY

    Evaluated main@7bbbc8bb9b4acb859bc73ba2b861f657864cce5c.

    Current main push quality-gate: SUCCESS
    https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/30752494660/job/91508902082

    Current-baseline quality evidence:

    • Node v22.23.1 and pnpm 11.16.0;
    • frozen-lockfile install and pnpm check passed in the GitHub clean checkout;
    • report-schema public package import passed;
    • 8 test files / 340 tests passed / 0 failed.

    This is baseline evidence only. It is not the final M1 closure gate because the required Decision Engine and two STOP Fixtures are not yet merged into main.

    Completed:

    Outstanding:

    Tracker #4 remains Open / Project In Progress.
    M1 Milestone remains Open.
    No M2 handoff baseline is issued by this assessment.
    No M2 implementation is authorized by this assessment.

  12. pillowtalk-Qy commented on Aug 3, 2026

    @pillowtalk-Qy
    ContributorAuthor

    POST_ISSUE_6_EXECUTION_INDEX

    Merged baseline: main@aa7ea761b2ac5e78535387e0a7d04d45485cdfb1
    Merged-main push quality-gate: SUCCESS, https://github.com/Moss-Mini-Demo/moss-mini-demo/actions/runs/30833497929/job/91752910028

    Current M1 execution state:

    Current serial order: #8 -> #20 -> #9 -> Tracker #4 closure assessment.

    Qy may work on only one Fixture issue at a time. #20 remains unclaimed while #8 is In Progress. No implementation, branch, PR, Review, Merge Gate, or merge is authorized by this status record.

  13. pillowtalk-Qy commented on Aug 5, 2026

    @pillowtalk-Qy
    ContributorAuthor

    M1_CLOSURE_PASS

    Assessment baseline: main@aae0397da1ba4924422d5a456123e9a4243b1797

    Merged-main evidence:

    Independent Maintainer closure assessment:

    Conclusion: M1 satisfies the recorded closure criteria on the exact main baseline above.

    Tracker #4 may be closed as Completed / Project Done and the M1 Milestone may be closed. This assessment does not itself implement M2 or authorize any M2 Issue beyond the separate post-closure execution-slot update.

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Assignees

No one assigned

    Labels

    Type

    No type

    Projects

    No projects

      Relationships

      None yet

      Development

      No branches or pull requests

      Issue actions